The table sits near the bottom of a budget page on a website run by an owner at Jupiter Bay, a 359-unit condominium community in Jupiter. It splits a concrete restoration project of more than $7 million into building-by-building special assessments. Per unit, a West E owner is listed at $27,074. A Villa D owner is listed at $0.

These owners share one community name, the same pools and the same entry. The repair bills attached to their units differ by tens of thousands of dollars. That gap is a direct product of Florida's post-Surfside condominium rules, and it reaches every buyer comparing condos in Jupiter right now. In a complex with several buildings, the building letter and the contract rider can shape your first two years of ownership more than the asking price does.

One Community, Ten Assessment Lines

Here is how the Jupiter Bay Viewpoint budget page lays out the concrete remediation assessments. The site is owner-run, not an independent news source. It labels some figures announced and others estimated:

Building Phase Status Total repair cost Per-unit assessment
West A 1 Announced $894,160 $23,630
West B 1 Announced $774,965 $22,027
West C 1 Announced $717,079 $19,823
East D 2 Estimated $427,717 $42
Villa D 2 Estimated $42,230 $0
West D 3 Announced $799,800 $19,340
West E 3 Announced $1,077,536 $27,074
West F 3 Announced $795,063 $18,251
East A 4 Estimated $893,315 $6,038
East B 4 Estimated $873,487 $5,891

The pattern isn't explained by repair cost alone. East D's repair estimate of $427,717 is roughly half of West A's, yet its assessment is $42 instead of $23,630. What separates them is reserves on hand. East D entered 2026 with $265,534 in reserves and a planned 2026 contribution of $156,488, which leaves a shortfall of $5,695 to spread across 135 units. West A had $137,985 in reserves against nearly $900,000 in work, which left a shortfall of $756,175 for 32 units to cover.

Unit count matters as much as the bank balance. The same site describes the East association as 135 units and each West building as 32. A shortfall of the same size, divided among 32 owners instead of 135, produces a per-unit bill about four times larger.

The site's author also disputes the engineering recommendations behind the repairs. Whatever you make of that dispute, the per-unit numbers are what a buyer's contract will have to address.

Why the Bill Arrives as a Lump Sum

State law has pushed regular reserve funding up. According to the owner site, Jupiter Bay's structural integrity reserve study required reserve contributions 34.69% higher starting in 2026. Those contributions accounted for the entire 2026 budget increase, and owners can no longer reduce or waive them by vote. Average maintenance fees reached $990.25 a month in 2026, up 73.5% from about $571 a month in 2020.

The association's own governing documents are what turned the repairs into one-time checks. The site says the bylaws require consent from two-thirds of unit owners to borrow more than $75,000. It credits that threshold with forcing the concrete work to be funded through special assessments rather than a loan spread over time.

A buyer can check the borrowing rule before making an offer. Two associations with identical repair needs can hand owners very different cash demands, depending on whether their bylaws let the board finance the work. The declaration and bylaws are among the documents a resale seller has to provide. Reading the borrowing clause tells you whether a future repair is more likely to show up as a higher monthly fee or as a single assessment.

Who Pays Depends on a Box in the Condo Rider

Once an assessment exists, the Florida Realtors/Florida Bar Condominium Rider decides how it is split between seller and buyer. The current version took effect July 1, 2025. Its default rules work like this:

  1. Levied by the effective date. By default the seller pays in full at or before closing. The form also lets the parties choose the buyer instead.
  2. Payable in installments. The seller pays installments due on or before closing. If the box is left blank, the buyer picks up installments due after closing. If the seller is selected, the seller pays the full assessment. The seller also pays in full if the association won't let the buyer assume the remaining installments.
  3. Imposed after the effective date and not pending. The cost is split by due date. The seller pays what comes due before closing and the buyer pays what comes due after.
  4. Pending. The rider's disclosure covers assessments that appeared on an association agenda or in meeting minutes during the prior 12 months.
  5. Not disclosed. If a seller fails to disclose an existing levied or pending assessment, the seller pays it in full at closing.

At Jupiter Bay, the owner site's original schedule for Phase 1 runs June 1 through December 31, 2025, for West A; January 1 through March 31, 2026, for West B; and April 1 through December 31, 2026, for West C. The later phases are where timing matters. A West E unit under contract while its $27,074 figure is still an agenda item is in a different position from one where the assessment has already been levied and scheduled. Under the rider, an assessment counts as levied once it is approved as required by Florida law and the condominium documents. The rider asks for the amount only "if known." The form doesn't say how to handle an assessment that has been disclosed but has no final figure yet. Negotiation fills that gap.

The Estoppel Certificate Puts the Numbers in Writing

The rider assigns responsibility. The estoppel certificate supplies the figures. Under section 718.116(8), the association must itemize every assessment and special assessment owed when the certificate is issued. It must also separately itemize special assessments scheduled to come due on each day the certificate is in effect.

The association has 10 business days to issue the certificate. It stays effective for 30 days if it is delivered by hand or electronically, and 35 days if it is sent by regular mail. If closing slips past that window, a certificate that covered one installment may not cover the next.

The fees are capped. The Florida DBPR's posted schedule sets the CPI-adjusted limits at $299 for preparation, an extra $119 for delivery within three business days, and up to $179 more if the account is delinquent. The next adjustment is due by July 1, 2027.

Seven Business Days With the Structural Paperwork

Florida's resale statute sets a clock for the documents that explain the assessments. A seller must provide the declaration, articles, bylaws and rules, the latest annual financial statement and budget, the inspector's summary of the milestone inspection where one applies, and the most recent structural integrity reserve study or a statement that one hasn't been completed.

The 2026 text of section 718.503 gives the buyer two separate cancellation windows of 7 days each, excluding weekends and legal holidays. One runs from receipt of the governing and financial documents. The other runs from receipt of the milestone summary and reserve study. The buyer may extend closing by up to 7 such days, any waiver of these rights has no effect, and the right to cancel ends at closing. If an association is required to complete a milestone inspection or reserve study and hasn't, the contract must say so in conspicuous type.

The reports are only as useful as the reporting system behind them. The Palm Beach Post reported on July 31, 2026, that a state study listed no unsafe condominium complexes in the Palm Beaches, but 17 of 39 municipal building officials had not submitted the required milestone-inspection data. The association's own documents, read building by building, remain the most direct record a buyer has.

The County Market Gives Condo Buyers Room to Negotiate the Details

None of this points to a falling market. In August 2026, Palm Beach County's townhouse and condo median sale price was $300,000, up 5.3% from $285,000 a year earlier, according to the Realtors of the Palm Beaches & Greater Fort Lauderdale August snapshot. Active listings fell 17.1% to 5,770, and supply tightened from 9.0 months to 6.7. Sellers received 92.6% of original list price, up from 90.3%, and the median time to contract was 69 days.

The single-family comparison shows where condo buyers have room. In the same August 2026 report, single-family homes had 3.5 months of supply and a 40-day median to contract. Condo buyers face nearly twice the supply and wait longer to reach contract, which leaves room to negotiate terms. Who pays a pending assessment, and when, is one of those terms. These are countywide figures, since no Jupiter-specific August series was available, but the spread between the two property types is wide enough to matter in Jupiter as well.

A Few Quick Answers

Does a low monthly fee mean a building is in better shape? Not on its own. At Jupiter Bay, the deciding factor was reserves on hand compared with repair cost, which the monthly fee doesn't show. The budget and reserve study do.

If an assessment is only being discussed, is it disclosed? Under the Condo Rider, an assessment that appeared on an association agenda or in meeting minutes within the prior 12 months counts as pending and falls within the disclosure.

Can a buyer take over an assessment's remaining installments? The rider allows it if the association permits assumption. If the association doesn't, the seller pays in full.

If you're weighing two Jupiter condos with similar asking prices, or preparing a unit in a building with an assessment on its calendar, Jeanne Gordon can go through the reserve figures, the bylaws and the rider allocation with you before those numbers are set in a contract. Owners who want to know how a pending assessment affects their unit's value can start by requesting a home valuation.

This article is general information, not legal, tax or financial advice. Consult a qualified professional about your situation.

Work With Jeanne

Get assistance in determining current property value, crafting a competitive offer, writing and negotiating a contract, and much more. Contact me today.